Gemini 7 Technical Debriefing, 1965
NASA-UAP-D021 · page 186 of 222
Text
This text came with the file. It may have mistakes. When the text and the image disagree, the image is right.
176 Lovell There is no doubt about it. The only way you can plan a mission of this length of time is real time flight planning. Call up the data you want for the day, it is a regular work day schedule. Call up what you want, and we will put it down and we will work at it; we will run it off that night. 12.3 Spacecraft Changes Borman I do not know of one major change in the spacecraft that we wanted that we did not get. GPO was very cooperative about everything. Of course, the big thing that we wanted, that we got after a hassel, was the ability to operate suits off. We planned this from the beginning with our first stowage review, and we finally made it by going the route of getting the suits that we could take off. And I think this contributed much to the satisfactory completion of the mission. Don't you? I have got personal notes here that were made during the flight. Every other page it says suits off was the only way to go, "I do not know how I stayed in the suit for six days," and so on. The suit I am sure has done more to increase the bugaboo of physical deterioration in space flight than a:n:y other single item. Fa.r more than zero g.