46
Conrad
It seems to me we ' ve got some data for them on Primary
scanner over the states so they could h~ve it on telemetry,
They should be able to find out what happened on that,
Cooper
Yes, something was really fouled up, I think,
Insertion
Check List-­
Conrad
We went through it by the numbers ,
Cooper
By the numbers , Thruster and Control Mode Check - we went
t hrough by the numbers.
Everything was fine .
Conrad
Well, we were a little bit late,
We get a little bit
behind and it was about the time when we were late per­
forming the thruster control mode check because that was
supposed to be done before you got to the Canaries and
we did it after the Canaries .
Cooper
That' s right,
Conrad
We were behind, but we started catchine: up.
,